By the Design Team at Elegante Interiors, Bengaluru | Published 10 November 2026
Most flat possession checklists are written for one moment: the walkthrough with the builder’s site engineer. They check whether the tap runs and the door shuts. They rarely check the things that turn into expensive problems after your wardrobes, modular kitchen and false ceiling are in.
This gap matters more than most homeowners realise. A damp patch on a bare wall is the builder’s job to fix. The same patch, found six months later behind a ₹1.5 lakh wardrobe, means taking the wardrobe off the wall, waiting for the repair to dry, and arguing about who caused it.
This snag list is written from the other side of the job: the interior side. It covers the usual possession checks, and adds the ones that decide whether your interiors can go in cleanly.
Quick answer: Before you start interiors on a new flat in Bangalore, inspect it in daylight with a moisture meter, spirit level, socket tester, measuring tape and a bucket of water. Check walls for dampness and hollow plaster, floors for hollow or uneven tiles, bathrooms for slope and leaks, and the exact positions of kitchen plumbing, gas and electrical points. Send the builder a dated, photographed snag list by email and get the repairs signed off before any carpentry starts. Under RERA Section 14(3), defects reported within five years of possession must be fixed by the builder, but proving a defect is far easier on a bare wall.
If you are still planning the interior budget itself, our interior design cost guide for Bangalore covers that. This post is about what to do before that money is spent.
Why the snag list has to happen before interiors, not after
The real reason is not the law. The law is on your side either way. Section 14(3) of the Real Estate (Regulation and Development) Act, 2016 makes the builder responsible for structural defects and defects in workmanship, quality or services that are reported within five years of possession. If the builder does not fix them within 30 days, you can claim compensation through the state RERA authority.
What most people miss is the exclusion list. Explainers on the Act, such as this one from Housing.com, note that damage caused by the buyer’s own installations or modifications is generally not the builder’s responsibility. Once a carpenter has drilled 40 holes into a wall for a wardrobe and a TV unit, a builder can argue that the crack or leak came from the interior work. On a bare wall, there is no argument.
Karnataka RERA has ordered builders to repair seepage after possession. In one case reported by The Realty Today in July 2025, K-RERA directed a developer in north Bengaluru to carry out permanent repairs to seepage in a flat’s internal walls, after the buyer’s earlier complaints had gone unresolved. The buyer won, but it took months. Months during which no interior designer should be fixing woodwork to those walls.
The operational reality: a defect you find before interiors costs you a phone call. The same defect found after interiors costs you a dismantle, a repair and a re-install, and you may pay for at least one of those.
What to carry to the inspection
You do not need to hire a professional inspector for a standard apartment, although it is worth it for a villa or a resale flat. You do need the right tools. Most of them cost less than a dinner out.
| Tool | What it catches | Approx. cost |
|---|---|---|
| Pin or pinless moisture meter | Hidden dampness in walls before it shows as paint bubbles | ₹1,000–₹3,000 (some paint brands offer free tests) |
| Spirit level (2 ft) or laser level | Out-of-plumb walls, sloping floors and platforms | ₹300–₹2,500 |
| 3-pin socket tester | Missing earth, reversed live and neutral | ₹300–₹600 |
| Measuring tape (5 m) and floor plan printout | Wrong room sizes, point positions, ceiling heights | ₹200 |
| Bucket of water and a small ball or marble | Bathroom and balcony floor slope, drain flow | — |
| Torch and phone camera (timestamp on) | Cracks in corners, evidence for your snag list | — |
| Masking tape and a marker | Marking each defect so the builder’s team fixes the right spot | ₹100 |
Two timing tips that guides rarely mention. First, inspect in daylight. Tube lights hide uneven plaster and tile lippage; low-angle sunlight shows them. Second, if you can choose, inspect after rain. Bangalore gets two monsoons, the south-west from June to September and the north-east in October and November. Seepage that hides in February shows up in November.
The room-by-room flat possession snag list (with the interior checks added)
Each check below has a pass condition. Where a check matters specifically for interiors, we say why.
Walls and plaster
- 1. Moisture reading on every wall that will get a wardrobe, TV unit or wall panel. Pay special attention to external walls and walls shared with a bathroom or kitchen. If the reading is high, ask for the source to be traced, not just painted over. (Paint brands publish their own scales: Berger’s Homeshield meter guidance, for example, puts readings of 0–5 in the “regular painting” band and anything above 10 in the “needs waterproofing” band.)
- 2. Tap test for hollow plaster. Knock along the wall with your knuckle or a coin. A dull, hollow sound means the plaster has separated. It will crack when a carpenter drills into it.
- 3. Cracks at corners, around windows and above door frames. Hairline shrinkage cracks are common in new plaster. Diagonal cracks or anything you can fit a coin edge into should go on the list.
- 4. Wall plumb on wardrobe and kitchen walls. Hold the spirit level vertically. A wall that leans by more than a few millimetres over its height leaves a visible gap beside a full-height wardrobe. It can be packed out, but it costs time and material.
- 5. Wall-to-wall squareness in the kitchen. Measure both diagonals of the kitchen floor. If they differ noticeably, the corners are not square, and your modular kitchen designer needs to know before taking measurements.
- 6. Paint finish: patches, roller marks and touch-ups in a different shade. Minor, but it is the builder’s job.
Floors and tiles
- 7. Hollow tiles. Tap every tile, or roll a coin or a key across them. Hollow tiles crack under the weight of a loaded wardrobe or a kitchen base unit.
- 8. Lippage: one tile edge higher than its neighbour. Run your palm across joints. It matters most where a wardrobe or kitchen plinth will sit.
- 9. Floor level across the room. Place the spirit level in three or four spots. A floor that slopes will make wardrobe shutters drift open unless the carpenter adjusts for it.
- 10. Grout: missing, cracked or stained joints, especially near the kitchen and bathroom doors.
- 11. Skirting: loose pieces, and gaps between skirting and wall. Note the skirting height; it affects how wardrobes and kitchen plinths are detailed.
Ceilings
- 12. Seepage marks or bubbling paint on the ceiling, especially below the bathrooms of the flat above. Once a false ceiling goes up, these stay hidden until water drips through the board.
- 13. Clear ceiling height in every room, measured floor to slab and floor to the underside of any beam. A false ceiling usually takes 6 to 9 inches of height. If your bedroom is only around 9 feet 6 inches to the slab, your designer may suggest a peripheral ceiling instead of a full one.
- 14. Beam drops and their positions. Note them on your floor plan. They decide where cove lighting, curtain pelmets and full-height wardrobes can go.
If you are weighing ceiling materials for a damp-prone room, read our guide to calcium silicate false ceilings, which handle moisture better than standard gypsum.
Kitchen: the check most people get wrong
In practice, the kitchen is where possession checks and interior design collide hardest. Your modular kitchen layout is planned around points the builder has already fixed in the wall. If those points are in the wrong place, the kitchen design has to bend around them, or someone has to break tiles to move them.
- 15. Sink inlet and drain position. Measure from the nearest corner. The drain should fall where you want the sink, and it should flow freely. Pour a bucket of water down it.
- 16. Gas pipeline entry point (piped gas or cylinder bank): position, height, and whether it clashes with where you want the hob.
- 17. Chimney point and exhaust cut-out. Check there is an electrical point above the hob position and a core cut through the external wall for the chimney duct.
- 18. Electrical points for fridge, microwave, RO purifier, dishwasher and mixer: count them, note their heights, and check each with the socket tester.
- 19. Wall tiles behind the counter: hollowness and lippage, as above. Your backsplash and wall units will be screwed through them.
- 20. Builder-supplied granite platform, if any: level it with the spirit level, and check the edges for chips. Many modern buyers remove it for a fully modular kitchen, so tell the builder early whether you want it.
- 21. Utility area drain and washing machine inlet: test both with water.
If you already know you want a modular kitchen, our guide to kitchen materials that survive Bangalore’s humidity and our modular kitchen cost breakdown will help you decide what to tell the builder to leave or remove.
Bathrooms
- 22. Floor slope test. Pour a bucket of water. It should drain fully to the floor trap, with no ponding near the door or the shower area.
- 23. Leak test below. Ask the builder (or your downstairs neighbour, if the flat below is occupied) to let you check the ceiling under your bathrooms after you have run water for 15 minutes. Leaks there almost always mean the waterproofing needs redoing.
- 24. Every tap, mixer, flush and health faucet: pressure, hot and cold correct way round, no drips at the joints.
- 25. Geyser point and exhaust fan point: present, working, and the geyser point on its own circuit.
- 26. Silicone and grout around the WC, washbasin and shower: continuous, no gaps.
- 27. Bathroom door bottom: water-resistant frame or a raised threshold, so water does not soak the frame and spread into the bedroom wall, which is often the wall your wardrobe goes on.
Electrical
- 28. Distribution board labelling. Every circuit should be labelled. Unlabelled boards slow down every electrician who ever works in your home, including ours.
- 29. RCCB/ELCB trip test. Press the test button. It should trip immediately.
- 30. Every socket with the 3-pin tester. No missing earth, no reversed polarity.
- 31. AC points and core cuts in every bedroom and the living room: position, height, and whether the core cut lines up with where the outdoor unit can sit.
- 32. TV, data and set-top box points: height and position. Note these on your plan; your TV unit design starts from here.
- 33. Bedside switch and socket points: check they fall either side of where the bed will go, not behind a future wardrobe.
- 34. Light points in each room: working, and the ceiling points not sitting directly under a beam.
Point positions are the most common reason a design has to change on site. Photograph each wall with its points visible and a tape held across it for scale. Your designer will thank you, and our first-consultation checklist explains what else to bring to that meeting.
Doors, windows and balconies
- 35. Every door: shuts without scraping the floor, the lock works, and the gap around the frame is even.
- 36. Main door: the lock, the peephole and the door closer if fitted. Check for a gap at the bottom.
- 37. Windows: slide or open smoothly, lock properly and seal. Pour a mug of water along the outside track of sliding windows and check that it drains out, not in.
- 38. Window grills and glass: no cracks, scratches or loose beading.
- 39. Balcony slope and drain: the same bucket test as the bathroom. Water should run away from the living room door.
- 40. Balcony railing: firm, with the height the approved plans show.
Documents and utilities
This post is about the physical flat, so we will keep this brief. Make sure you receive the Occupancy Certificate (or confirmation it has been applied for), electricity and water meter details, the warranty cards for any fittings the builder supplied, and the approved floor plan. Keep the plan safe: your interior designer needs it.
- 41. Meter readings at handover, photographed with the date visible, so you only pay from your possession date.
- 42. All keys, including those for the electrical duct, shaft door and letterbox, counted against the handover sheet.
Which defects cost the most if you find them after interiors
Not every snag is equal. This is how we rank them, based on how much interior work has to come apart to fix them.
| Defect | If found before interiors | If found after interiors |
|---|---|---|
| Wall dampness or seepage | Builder traces and fixes the source; wall dries; you paint | Wardrobe or panel removed, repair, drying time, re-install; risk of swollen board |
| Leak from the flat above or your own bathroom | Builder redoes waterproofing | False ceiling opened or replaced; stains on finished paint |
| Wrong sink, gas or chimney point position | Builder moves the point; kitchen designed around the final position | Kitchen redesign or tiles broken to move points |
| Hollow tiles under a wardrobe or kitchen | Builder relays the tiles | Units moved out; matching tiles may no longer be available |
| Out-of-plumb or out-of-square walls | Designer plans fillers and scribes in advance | Visible gaps, or a unit that will not fit |
| Missing earth or a faulty circuit | Builder fixes it at the board | Wall chased behind a finished unit |
Most guides ignore the second-order cost: time. In our experience, a single seepage problem found during installation can hold up a project for weeks, because no reputable team will fix plywood to a wall that is still drying.
How to submit your snag list so it actually gets fixed
- Mark and photograph every defect. Put a strip of masking tape on each one with a number, and photograph it with the timestamp on.
- Write it up as one document. Number, room, location, description, photo. A spreadsheet or a shared document works.
- Send it by email to the builder’s CRM or customer care, not just WhatsApp to the site engineer. Email gives you a dated record, which matters if you ever need RERA.
- Ask for a written acknowledgement and a target date for each item.
- Re-inspect with the same list and sign off item by item. Do not accept “it will settle” for dampness; ask to see the meter reading drop.
- Only then give your interior team the go-ahead for final site measurement.
If the builder refuses or delays beyond 30 days, keep your emails and photographs. They are the evidence a RERA complaint needs. We are interior designers, not lawyers, so for a dispute that reaches that stage, speak to a property lawyer.
Five mistakes we see new homeowners make
- Accepting “we will fix it after you move in.” After move-in, every repair happens around your furniture and your interiors, and the builder’s team works less carefully in an occupied home.
- Doing the inspection at 6 pm. Artificial light hides most wall and floor defects.
- Letting the painter cover a damp patch. Fresh paint hides dampness for a few weeks at most. Ask for the source to be fixed first.
- Booking carpentry before the snag list is closed. It feels efficient. It usually adds weeks.
- Not sharing the snag list with the interior designer. A good designer plans around the defects that remain, such as a slightly out-of-plumb wall, instead of discovering them on installation day.
Where your interior designer fits in
Modular interiors are manufactured to measurements taken on site. The panels in a wardrobe or kitchen are cut and edge-banded in a factory weeks before they reach your flat. So the condition of the site on measurement day sets the quality of everything that follows.
At Elegante Interiors, our site measurement visit is also when we look at the things in this list that affect the design: dampness on wardrobe walls, point positions in the kitchen, ceiling heights and beam drops. If we find a builder defect, we tell you before we design around it, so you can raise it with the builder while it is still their responsibility. You can see how this fits into a full project in our 45-day 3BHK project timeline, and how a single team handles the whole job in our turnkey interior design guide.
Just got your keys? Book a site visit with our design team and bring your snag list. Or use our interior price calculator to get a starting budget for your flat while the builder works through the repairs.
Frequently asked questions
What should I check before taking possession of a flat in Bangalore?
Check walls for dampness, cracks and hollow plaster; floors for hollow or uneven tiles; bathrooms for floor slope, leaks and working fittings; every electrical socket for earthing; doors and windows for alignment and water-tightness; and the positions of kitchen plumbing, gas and electrical points. Inspect in daylight, carry a moisture meter, spirit level and socket tester, and send the builder a numbered, photographed list by email.
Should I start interiors before the builder fixes the snag list?
No. Wait until the defects that affect walls, floors, ceilings and kitchen points are fixed and signed off. Once wardrobes, a modular kitchen or a false ceiling are installed, repairs mean dismantling your interiors, and the builder can argue that the damage came from the interior work. Minor items such as a loose door handle can be fixed in parallel.
How long is the builder responsible for defects under RERA?
Under Section 14(3) of the RERA Act, 2016, the builder is responsible for structural defects and defects in workmanship, quality or services that are brought to their notice within five years of possession. They should fix them within 30 days at no cost to you. If they do not, you can approach the state RERA authority, which in Bangalore is Karnataka RERA, for compensation.
How do I check a new flat for dampness?
Use a moisture meter on every wall, especially external walls and walls shared with bathrooms and kitchens. Look for bubbling paint, white powdery patches and a musty smell, and check the ceiling below the bathrooms of the flat above. The best time to check is just after rain. Some paint brands offer free moisture tests if you do not want to buy a meter.
How much ceiling height do I need for a false ceiling?
A false ceiling usually takes 6 to 9 inches of height, depending on the lighting and whether it hides beams or AC ducting. Measure from the floor to the slab and to the underside of every beam during your possession inspection. In rooms with a low slab, a peripheral false ceiling around the edges keeps more height in the middle of the room.
Should I hire a professional home inspector for a new flat?
For a standard new apartment, a careful owner with the right tools can catch most defects using a checklist like this one. A professional inspector is worth paying for if you are buying a villa, a resale flat, or a project with known quality complaints, because they bring thermal cameras and experience of what usually goes wrong in a particular building.